Tuff Tube Transition: The Solution to Power Plant Tube Failures
Engineered for Quality, Efficiency, and Minimal Downtime
Tube failures are a critical issue that can bring a power plant’s operations to a sudden, grinding halt. Recognizing the need for a more efficient and reliable repair solution, Tuff Tube Transition product line was developed — an ASME Section I compliant part designed to minimize downtime and costs while improving the quality and reliability of tube-to-tube and tube-to-header connections.
Save on repair time and reduce costly outages.
A secure, oxidation-free connection means safer and longer-lasting repairs.
Get back online faster, with repairs that take hours, not days.
Don’t wait for the next tube failure to disrupt your operations. Be proactive with Tuff Tube Transitions — the fast, efficient solution to eliminate downtime and maximize your plant's performance.
To ensure you're ready when the time comes, we recommend preordering Tuff Tube Transitions for your HRSG sections and keeping them in stock at your facility. With a standard lead time of just 6–8 weeks, you'll have peace of mind knowing TTT products are available for immediate use, WHEN a tube failure occurs.
Quick, easy repairs in a fraction of the time when in stock.
Standard, expedited, and emergency expedited options available.
Tuff Tube Transition has developed a high quality, and extremely efficient process to replace stubbed-headers in a HRSG system. These innovative TTT-lined headers provide a significant gain in installation production time, quality of installation, and with a significant improvement in strength over conventional stubbed-headers with comparable engineering analysis.
Scope: Replacement of 3 RH1 Lower Headers // Material: 22 Grade (2-1/4 chrome)
A conventional stubbed-header install, with a minimum of 12 personnel, would be a 5-6 week, 24/7 operation.
In this instance, from removal of existing headers, to the complete installation of new TTT-lined headers, involving an installation crew of 12 personnel, the install duration amounted to a minimal four days.
In this instance, TTT-lined header provided 85-90% savings in downtime to the plant.
In conjunction, FEA stress analysis performed for this installation, shows TTT-lined header to have a 53% gain in service durability over a conventional stubbed header.
Order Tuff Tube Transitions now and ensure your facility is ready to tackle tube failures quickly and effectively.
Contact us to learn more about how TTT can save you time, money, and headaches during your next repair or new unit purchase or technology eliminates old problems in conventional units.